Substructure
Completed deck substructure is ready for the new Procell decking surface (Refer to Illustration B)

NOTE: With this method of installation you will need to install some additional joists to support the outer deck plank where it runs parallel to the main joists.

Mitre Cut
Miter cut the corners and lay down the perimeter planking to form the "picture frame" as shown above.
Fasten Frame
Be sure to let the deck plank overhang the rim joist 1/2" up to 1" as shown above. Check for proper fit at each miter cut. Then begin fastening the perimeter planking in place using screws at each joist at 16" on center max.
Azek Deck Installation Azek Deck Installation Azek Deck Installation
Proper Spacing
Use your preferred spacing method to allow for the 1/8" to 1/4" gap between planks. Fasten planks using 2 screws per joist.
Finish Install
Continue to attach planks until surface is complete.
Cover Rim Joist
Use deck planks or rim joist cover (fascia) to cover the rim joist as shown above. For rim joist installation see steps 11 and 12. Miter cutting the corners will provide a clean, finished look.
Azek Dec Installation   Illustration A
Azek Deck Installation
  Illustration B
Azek Deck Installation
  Illustration C
Azek Deck Installation
Basic Installation Substructure
16" on center max. (12" for commercial applications) joists.
Picture Frame Installation Substructure
16" on center max. (12" for commercial applications) joists plus additional support for the picture frame structure.
Diagonal Installation Substructure
12" on center max joists.